Work continues on the BCV 2.0 project! Here are the Byrne Cortlandville expansion updates for the week ending Oct. 3, 2025: Traffic diverted on new road Basic signage complete Scale relocation complete Foundation & walls ongoing Steel erection in progress Phase A underground piping High voltage electrical prep in progress Raw Bay exit closed; Raw… The post Byrne Cortlandville Expansion Updates: Oct. 3, 2025 first appeared on Byrne Dairy.| Byrne Dairy
Check out our recent progress on the Byrne Cortlandville expansion for the week ending Sept. 26, 2025: Road Paving is mostly complete, and the new entry road will be open for use this weekend. Phase A underground Plumbing and Foundation Walls Raw Bay 1 Exit Closed through 10/1/25 Steel is positioned, and erection begins Monday, 9/29/25… The post Byrne Cortlandville Expansion Update: Sept. 26, 2025 first appeared on Byrne Dairy.| Byrne Dairy
Work on the Byrne Cortlandville 2.0 expansion continues. Here are the updates for the week ending Sept. 5, 2025: Lift station tie-in and the receiving exit opening will be soon. Ammonia work was conducted, and the diffusion tank was removed. Boiler work for the plant. Lobby/Elevator excavation / Foundation complete and refilled. New employee drive… The post Byrne Cortlandville Expansion Update: Sept. 5, 2025 first appeared on Byrne Dairy.| Byrne Dairy
On Thursday, July 17, we officially broke ground on the Byrne Cortlandville expansion. BCV employees, members of the Byrne family, and our community and business partners gathered to celebrate the biggest project in Byrne history! The $120 million expansion project will double the workforce and production capacity at BCV. Stay tuned for more news of… The post Byrne Dairy breaks ground on Byrne Cortlandville expansion first appeared on Byrne Dairy.| Byrne Dairy