Work continues on the BCV 2.0 project! Here are the Byrne Cortlandville expansion updates for the week ending Oct. 3, 2025: Traffic diverted on new road Basic signage complete Scale relocation complete Foundation & walls ongoing Steel erection in progress Phase A underground piping High voltage electrical prep in progress Raw Bay exit closed; Raw… The post Byrne Cortlandville Expansion Updates: Oct. 3, 2025 first appeared on Byrne Dairy.